This is the Final Publication of the OCSRI Conservation Plan.

OCSRI Conservation Plan
Final 3/10/97
Chapter 17 Section C
Forestry

Oregon Coastal Salmon Restoration Initiative


Oregon Department of Forestry
OCSRI Workplans
February 19, 1997

Phase I Implementation Plan

ODF 1 - Road Erosion And Risk Project

Background: Many forest roads built prior to the development of the Oregon Forest Practices Act, or prior to establishment of the current Best Management Practices (BMPs), pose increased sediment risk to fish habitat. Industrial forest landowners have agreed to implement a voluntary program to identify risks from roads and to address those risks.

Goal: The goals of this project are to:

Roads assessed by this project will include all roads on non-federal forest land used as part of an industrial or state forest operation since 1972, regardless of their construction date. Emphasis will be given to road systems constructed prior to current forest practice standards and road systems in core areas.

Objective: This action will make improvements to road elements such as road fills, stream crossings, and drainage and surface problems to improve fish passage and habitat.

These improvements will also reduce the risks of adverse watershed effects associated with "legacy" roads and major storm events, such as the storm that occurred in February 1996.

The following priorities (highest priority listed first) will be used to implement this project:

Action Items:

Funding: The funding commitment for implementation of this project by OFIC landowners over the next ten years is estimated to be approximately $130 million, or $13 million per year on average. Technical support funding will be provided by ODF and DEQ.

Work Schedule:

Monitoring: This is a voluntary effort that will be monitored by ODF in cooperation with OFIC and ODFW. An annual accomplishment report by OFIC landowners and annual meetings will be used to measure progress. At the end of ten years, landowners will be evaluated on their substantive progress. For landowners who have not made substantive progress, more aggressive application of regulatory options will be considered.

ODF 2 - State Forest Lands Road Erosion And Risk Project.

Background: State forest landowners have agreed to implement a voluntary program (to include 1996 storm damage) on state-owned lands to identify risks from roads and to address those risks. This proposed effort will upgrade at least 130 miles of road in each of the next three biennium. Many of the road systems were built prior to the Oregon Forest Practices Act to salvage Tillamook burn timber in the 1950s. The state forestland was in private ownership at that time.

Goal: To restore, upgrade, and in some cases close state forest roads and stream crossing structures to meet current Forest Practices Act requirements.

Objective: The project will upgrade at least 130 miles of forest road in each of the next three biennium. This effort will reduce the risk of erosion and sedimentation that could severely impact fisheries resources.

Action Items: Roads will be inventoried using new road inventory protocol developed by ODF and OFIC to identify high priority road repair/improvement projects. Roads will be reconstructed, improved, or put to bed. All repairs and improvements will meet or exceed requirements of the revised Oregon Forest Practices Act rules.

Funding: Storm damage portion (FEMA and District storm-related costs): Current biennium $3 to $4 million anticipated.

For the Phase 2 portion of this measure $3 million dollars is available for the 97-99 biennium pending approval.

Road improvement program (Phase 2):
The Department is requesting authorization to spend an additional $3 million dollars and add 6.5 full-time equivalent (FTE) personnel as part of a program option package for the 97-99 biennium to support this portion of the program. The revenue to implement this project is available awaiting authorization.

Work Schedule: July 1996 through 2002

Monitoring: Reconstruction, road closures, and repair work will be monitored by ODF road engineers using GIS data collection techniques.

*******

ODF 3 - Technical And Policy Review Of Rules And Administrative Processes Related To Slope Stability

Background: To analyze the effects of the February 1996 and November 1996 storms, the Department is in the process of collecting and analyzing landslide information from study zones within the storm areas (reference ODF 13). As a followup of the monitoring effort, the Board of Forestry will review the existing forest practice rules and program in relation to slope stability to determine if changes in rules or administration procedures are needed. The review process will be two-fold, focusing on public safety and impacts on fish habitat and water quality.

Goal: Review forest practice rules related to slope stability.

Objectives:

Action Items: Water Quality/Habitat Issues

Adaptive Management

  1. Board of Forestry directs ODF to implement a technical/policy review of rules and administrative processes related to slope stability.
    • Complete data collection of two additional study sites under the Storms of 1996 Monitoring Project (ODF 13).
    • Vigorously pursue analysis of study data to determine frequency occurrence of landslides and potential water quality/habitat effects under different management scenarios.
    • Establish a technical group to assist ODF's review of rules and administrative processes.
    • Utilize existing scientific/technical literature related to landslides.

Regulatory Program

  1. Continue to apply high risk site rules/written plans.
  2. Increase compliance monitoring on road and harvesting practices on high risk sites.

Implement Voluntary Program

  1. Road erosion and risk project (ODF 1).
  2. State Forest Land Road Project (ODF 2).
  3. Retain In-unit trees along small Type N streams.
  4. Return all snags/downed wood within 20-foot RMAs along small Type N streams.
  5. Analyze effects of "rack" concept (ODF 61).

Public Safety/Property Issues

  1. Convene interim legislative committee to examine issues and make recommendations for addressing public safety/property damage issues by 1999 session.
  2. Board of Forestry requests voluntary deferral of forest practices on high risk sites meeting certain parameters for two years until legislative committee makes recommendations.
  3. Immediately implement project by ODF and state climatologist to develop reliable maps identifying public safety/property risks.
  4. Request Legislature to fund OEM, National Weather Service, and local public safety agencies to develop early warning system.
  5. ODF to provide notification of operation to residents that have homes in historic forest tracts below operations.
  6. Create hazard/risk notification protocol that can be used through local public safety agencies.

Funding: Funding of hazard mapping portion of this project will be contained within ODF's forest practices budget.

Work Schedule:

Monitoring: Annual reporting.

*****

ODF 4 - Stream Habitat Assessments.

Background: For the last three years, industrial forest landowners and state forest lands have contracted with ODFW to complete stream habitat surveys following modified Hankin and Reeves protocol (ODFW protocol).

Assessments, to date, have included approximately 3,000 miles of stream. Landowners plan to continue to provide funding for, or conduct, additional assessments during the next several years. The focus of these assessments will be completing all coho streams.

Goal: Assess the condition of salmonid habitat in all coastal watersheds, at a target of approximately 1,000 miles per year.

Objective: See ODFW measure I.B.2.

Action Items: See ODFW measure I.B.2. (Responsibilities).

Funding: See ODFW measure I.B.2.

Work Schedule: See ODFW measure I.B.2.

Monitoring: Annual reporting.

ODF 5 - North Coast Salmonid Habitat Restoration Project

Background: The North Coast Salmonid Habitat Restoration Project is an existing program that has been in place for two years. Membership is open to all landowners who share a commitment to stream habitat conservation, restoration, and enhancement through cooperative means and who can contribute valuable resources (time, equipment, and funding) to support the Project's objectives.

A steering committee oversees the project. Representatives on the steering committee include a representative of each landowner; a representative from each of the Oregon Department of Fish and Wildlife, Oregon Forest Industries Council, Oregon Small Woodlands Association, and the Associated Oregon Loggers; and two representatives from the Oregon Wildlife Heritage Foundation.

The geographic area this project encompasses includes all river basins from Neskowin Creek near Lincoln City north to the mouth of the Columbia River. The area is divided into three regions: the Nehalem, the Tillamook and the Nestucca. Approximately 64 original potential restoration sites were located within the project area during the first two years. An additional 92 potential project sites have recently been identified on state forestland by ODFW through a three-month contract funded by ODF. Work will also begin during 1997 to identify additional habitat improvement projects on private lands.

Goal: To conserve, restore, and enhance salmonid habitat of the North Coast through voluntary participation of area landowners in cooperation with the Oregon Wildlife Heritage Foundation and the Oregon Department of Fish and Wildlife.

Objective: The development and implementation of detailed habitat restoration plans for individual stream reaches identified in the Tillamook/North Coast and Lower Columbia Project Selection Guide developed by ODFW on private and state lands.

Action Items: Of the 64 total identified project areas for the Tillamook/North coast, 38 have been completed to date, 17 are scheduled to be completed in 1997, and 9 currently do not have scheduled completion dates. Contracts are being written to begin addressing the 92 projects on state forestland that are part of this Initiative.

Funding: Periodically, members of the Project may contribute money or something of value to the Foundation for the purpose of habitat restoration. The Foundation seeks contributions from other interested parties including federal agencies and private foundations. This money is used in part to fund an ODFW habitat biologist, to leverage additional federal funds, and to provide cost share dollars to small landowners who might otherwise not be able to afford projects on their lands.

Work Schedule: Current projects funded for completion (17 of which are currently in progress):

Monitoring: Completion of identified restoration projects. Monitoring of all the North Coast Initiative projects will occur using established protocol established by ODFW.

*******

ODF 6 - Mid-Coast Restoration Project

Background: The Mid-Coast Restoration Project has been modeled after the North Coast Restoration Project. Membership is open to all landowners who share a commitment to stream habitat conservation, restoration, and enhancement through cooperative means and who can contribute valuable resources (time, equipment, funding) to support the Project's objectives.

In 1996, the Mid-Coast Habitat Restoration Project completed 24 projects, including the placing of over 280 structures affecting approximately 21 miles of stream. Landowner participation included several industrial forest landowners (Boise Cascade, Georgia Pacific, Starker, Willamette, Simpson, Weyerhauser, Stimpson, Hampton, and Hancock), small private landowners, and Oregon Department of Forestry.

Goal: Conserve, restore, and enhance salmonid habitat (particularly Coho) of the Mid-Coast through voluntary participation of area landowners in cooperation with the Oregon Wildlife Heritage Foundation and the Oregon Department of Fish and Wildlife.

Objective: The development and implementation of detailed habitat restoration plans for individual stream reaches identified by ODFW.

Action Items: For 1997, a total of 26 potential projects have been identified within the Salmon, Siletz, Yaquina, Alsea, and Siuslaw basins. These potential projects include instream work, fencing, riparian planting, fish weir repair, maintenance, dike repair, and bridge installation. The potential projects could affect approximately 25 miles of stream reach. Five of the 26 potential projects are continuation of 1996 projects.

Funding: For 1996-97 and 1997-98, estimated funding is $850,000. Periodically, members of the Project may contribute money or something of value to the Foundation for the purpose of habitat restoration. This money is used to fund a habitat biologist hired by ODFW to implement projects and to leverage additional federal funds. The Foundation may also receive contributions from other interested parties.

Work Schedule: February 11, 1997 steering committee meets to determine 1997 project priorities.

Monitoring: Completion of identified restoration projects.

*****

ODF 7 - Fund Seven New Fish Biologists To Provide Technical Assistance For Salmonid Habitat Restoration

Background: This voluntary measure by the Oregon Forest Industries Council (OFIC) landowners will function to provide technical assistance in western Oregon to forest landowners conducting salmonid habitat restoration projects. Current in-place grassroots efforts, such as the North and Mid-coast initiatives (ODF 5 and 6) lack stable funding; this action will absorb these and create five additional areas covering all of western Oregon providing long-term stable funding. This project area will include the western slopes of the Cascades to the Pacific Ocean.

Goal: To conserve, restore, and enhance salmonid habitat in western Oregon through voluntary participation of area landowners in cooperation with the Oregon Wildlife Heritage Foundation, Oregon Department of Forestry, and the Oregon Department of Fish and Wildlife.

Objective: Provide technical support for the development and implementation of detailed habitat restoration plans and projects for individual stream reaches identified by ODFW.

Action Items: This program is in the initial phase of development.

Funding: OFIC forest landowners will voluntarily contribute up to $500,000 annually to fund seven biologists hired by ODFW. Additionally, in conjunction with the Oregon Wildlife Heritage Foundation, additional dollars will be leveraged to fund restoration projects on non-industrial forestland. On forest industry lands, restoration projects will be funded by the landowners.

Work Schedule: This program is in the initial phase of development; funding will be available spring of 1997. Restoration projects will be identified after biologists are on board and then prioritized for completion.

Monitoring: Completion of identified projects documented through annual reporting.

*******

ODF 8 - Riparian Hardwood Conversions.

Background: Forest practice rules adopted in the fall of 1994 affecting vegetation retention requirements have been changed to allow the conversion of conifer sites currently dominated by brush and hardwoods back to conifers.

This measure can only be implemented on conifer sites and only on sites where current RMA conifer basal area is half of that required by stream size and stream type under the general water protection rules. No more than half of the total stream length within the harvest unit can be converted, and the conversion blocks cannot exceed 500 feet in width. The conversion blocks must be separated from each other by a minimum of a 200-foot retention block where the general vegetation retention prescription is applied.

This management measure includes modifications of applications within initiative identified core areas. In lieu of the standard procedures within the rules, hardwood conversions within core areas will be subject to additional review and will require a site-specific plan to be submitted and reviewed.

Goal: To restore riparian conifers on conifer sites, while assuring potentially adverse effects are fully considered.

Objective: On sites where the native tree community would be conifer dominated, but due to historical events the stand has become dominated by hardwoods, in particular, red alder, the rules allow disturbance to produce conditions suitable for the re-establishment of conifer. In this and other situations where the existing streamside vegetation is incapable of developing characteristics of a mature streamside stand in a "timely manner," the desired action will provide functional stream shade, some woody debris, and bank stability in the short term while creating conditions in the streamside area to attain desired future conditions more quickly than would otherwise be achievable under natural succession.

Action Items:

Funding: Funding is within ODF Forest Practices budget.

Work Schedule:


Monitoring: Both validation and effectiveness monitoring have been initiated. Effectiveness monitoring will include analysis of riparian vegetation structure both pre- and post-operation and effectiveness of riparian reforestation efforts.

Implementation monitoring will analyze the frequency of hardwood conversions.

*****

ODF 9 - Northwest State Forest Lands Management Plan

Background: Oregon Department of Forestry is preparing a Northwest Oregon State Forest management Plan. A draft plan is expected to be completed by the summer of 1997. The plan will cover over 600,000 acres of state forest land and will address the full array of statutory mandates and Board and department policies. ODF is working closely with ODFW in developing the plan and has solicited input from stakeholders through a variety of forums.

Goal: To produce a forest plan that:

The plan will be used to develop a Habitat Conservation Plan, if possible, that serves as a means of complying with the federal ESA, and also achieves the purposes of the state ESA.

Objective: Plans are now in development and are not expected to be approved until late 1997. Riparian management practices focus on developing mature streamside stands to provide for the needs of multiple species. Watershed